A bathroom remodel in South Florida usually takes about a week for a refresh, 2 to 3 weeks for a full bath, and 3 to 5 weeks for a primary bath with a new shower or tub. A kitchen takes 1 to 2 weeks for a cabinet and countertop refresh and 6 to 10 weeks for a full remodel with layout changes. Those are the on-site numbers we use. The rest of the calendar is ordering, permits and inspections, and that is where most delays come from. This guide covers the phase-by-phase order of work, lead times, what slows jobs down in Miami-Dade, and how to live at home during construction. Looking at costs instead? See our kitchen remodel cost guide and bathroom remodel cost guide.
These are general industry ballpark ranges, not a GXG quote, and they cover construction after materials are in hand and permits are issued. They are estimates, and they change with scope, product availability and the condition of what is behind your walls. Published ranges from other sources are often longer. Golden Rule Builders lists 3 to 6 weeks for a mid-range bathroom and 6 weeks or more for a full renovation, and HGTV quotes 6 to 12 weeks for a regular kitchen renovation, not counting planning and design. When you compare, make sure each number includes the same things: planning, ordering, permits and construction are different clocks. Sources: Golden Rule Builders, HGTV.
From the first design meeting to the final walkthrough, Realm puts a full kitchen at 3 to 6 months, which is why deciding early is the best schedule move. Realm.
A bathroom is a small room where plumbing, electrical, waterproofing and tile all meet, so the work happens in a fixed order and each step has to finish before the next. Our service page breaks a full remodel into these steps:
Those day counts add up to roughly 2 to 3 weeks of working time, and calendar time is longer when trades are scheduled on different days or an inspection has to be booked. Two steps surprise people. First, waterproofing needs cure time, and the product maker sets how long to wait before tile goes on. Second, custom glass is often measured after the tile is finished and then fabricated, so ask how long the shower will wait for its door. Ask what is ordered and when.

A kitchen has more trades and more waiting. The sequence on our kitchen cost guide is: estimate, design and selections; permit review if required; ordering cabinets and stone; demolition and rough-in; inspections, drywall and flooring; cabinets, then countertop template and install; backsplash, fixtures, paint and punch list. USA Cabinet Store publishes typical durations for several of those steps, which are useful as a published range:
Source for the durations above: USA Cabinet Store, a national retailer, so treat them as published ranges and not as GXG quotes. The built-in gap to remember is the countertop: the fabricator measures after the cabinets are set and level, then cuts the stone, so a kitchen has cabinets but no tops for a stretch. Our countertop page covers materials and seams on countertop installation.

Lead time is how long a product takes to reach the job after it is ordered, and it is the most common reason a clean schedule slips. USA Cabinet Store lists these cabinet lead times from the order date:
The same source says the clock only starts when the order is complete, so a missing sink model or an unconfirmed appliance can hold the whole order. Bathrooms have their own long items: Golden Rule Builders notes that custom cabinets, specialty tile and glass enclosures can lengthen a project, without giving fixed numbers. We did not find a reliable published lead time for impact windows or custom shower glass, so we will not invent one. If your remodel includes new windows, ask the installer for the current lead time and for the product's Miami-Dade Notice of Acceptance, which is the county approval that impact products need. See our window installation page for what to ask.
Cosmetic updates like a new vanity, fixtures, paint, refacing or a countertop swap typically do not need a permit. Moving plumbing, electrical or gas lines, or changing the layout, generally does, and permits for that work are pulled by the licensed contractor. Miami-Dade County's permit exemption list names replacing kitchen cabinets in the same configuration, but related plumbing, ventilation and electrical work needs a permit if it is relocated or altered. The City of Homestead has its own Building Department, while homes in unincorporated areas fall under the county, so the rules and wait times depend on your address.
Permit review time is the number we cannot give you with confidence, because it changes with the department and the season. USA Cabinet Store cites roughly 6 to 8 weeks for a permit in its general ranges, and says timing varies by region, so treat that as a warning to ask early, not a local figure. Ask the building department that covers your address for its current review time, and ask your contractor when they will apply and who requests each inspection. The City of Miami notes that inspections are booked by the permit holder, and the same logic applies in other jurisdictions: the plumber, electrician and general contractor each hold their own sub-permit. Inspections happen before walls are closed, so a rough-in inspection sits between demolition and drywall, and a final inspection closes the permit. Florida's 2026 small-project exemption, as we understand it, does not cover plumbing and electrical work, so confirm with the department.
Many homes around Homestead, Florida City and Cutler Bay are concrete block and stucco on a slab, which changes a few schedules:
USA Cabinet Store lists these typical delays from its own experience: an incomplete order can lose 1 to 4 weeks at the factory, change orders after demolition can cost 1 to 2 weeks each, hidden conditions can add a few days to 4 weeks, and demolishing before materials arrive can leave you with no kitchen for weeks. The same list names permit and inspection queues and the wait for a contractor's start date. Here is how those play out in South Florida homes.
For a kitchen refresh you can often keep using the house, with a few days of limited use. For a full kitchen remodel, plan for a temporary kitchen for several weeks: a refrigerator, microwave or slow cooker, a table for a counter and a place to wash dishes, plus a takeout budget. For a bathroom, the question is whether you have a second one. If this is your only full bathroom, ask the contractor on which days the toilet and shower will be out of service, and plan showers elsewhere. Across both rooms, agree on work hours, dust control, where the crew parks and stores materials, and how pets and young children will be kept away from the work area.

The Atlantic hurricane season runs from June 1 to November 30. A storm threat can pause work, send crews to secure homes and delay deliveries, so ask any contractor what happens to your schedule and your open walls if a storm approaches. If your kitchen or bathroom project overlaps the season, ask about protecting exposed areas and about safe storage of materials. No month is guaranteed delay-free, so plan with a buffer.
On our service page we describe a half-bath refresh as about a week, a full bath as 2 to 3 weeks, and a primary bath with a full shower or tub conversion as 3 to 5 weeks. Published ranges from other contractors run longer for larger jobs: Golden Rule Builders, for example, lists 2 to 3 weeks for a small refresh and 3 to 6 weeks for a mid-range remodel. Special-order tile, custom glass and inspections are the usual reasons a schedule stretches.
On our kitchen pages, a cabinet and countertop refresh typically takes 1 to 2 weeks, a mid-range remodel with new cabinets in the same footprint 3 to 4 weeks, and a full renovation with layout changes and permits 6 to 10 weeks. HGTV quotes a regular kitchen renovation at 6 to 12 weeks, not counting planning and design. Cabinet and countertop lead times can add to the front end.
Usually yes, with a plan. For a refresh you may have a few days of limited use. For a full remodel, expect to run a temporary kitchen for several weeks: a refrigerator, microwave and a place to wash dishes in another room, plus extra takeout. Ask the contractor which days the water, power and gas will be off, how dust will be contained and what hours the crew works.
The installation itself is short. USA Cabinet Store lists cabinet installation at 3 to 5 days and countertop install at 1 to 2 days. The waiting is what takes time: cabinets often ship 2 to 14 weeks after the order depending on stock, semi-custom or custom lines, and stone fabrication after the template commonly takes 1 to 3 weeks. Ask for those dates in writing.
Measure and choose materials, order long-lead items, get permits if needed, demolish, do rough plumbing and electrical, pass inspection, close the walls, then flooring and tile or waterproofing. After that come cabinets or vanity, countertop template and install, backsplash, fixtures, paint and a final walkthrough. The countertop template cannot happen until cabinets are set and level.
The common causes are materials that arrive late, permits and inspections, hidden damage found once walls are open, and changes to the plan after work starts. Each is easier to manage when selections are final before demolition, long-lead items are ordered early, and the contract spells out how changes and surprises are handled.
There is no single answer we can verify. The Atlantic hurricane season runs June 1 to November 30, and a storm threat can pause work and delay deliveries, so ask any contractor how the schedule changes if that happens. Ordering early matters whatever the month.
It can. Moving plumbing, electrical or gas lines, or changing the layout generally needs a permit, and inspections are scheduled between phases. How long review takes depends on whether your address falls under unincorporated Miami-Dade or a city such as Homestead, so ask that building department for current turnaround before you plan dates. Cosmetic updates usually need no permit.
Every house has its own plumbing, walls and delivery dates, and a national article cannot see yours. The only schedule worth planning around is one written after someone has walked your kitchen or bathroom. See our kitchen remodeling and bathroom remodeling pages, or call (786) 724-5571 for a written, no-obligation estimate with a timeline.
Related guides: kitchen remodel cost, bathroom remodel cost and tile installation cost.
Our testimonials say
"GXG Remodeling repainted our whole exterior and it held up perfectly through the first rainy season. Clean job site, showed up on time every day."
"We had our kitchen cabinets painted instead of replaced and they look brand new. Saved us thousands and the crew was professional start to finish."
"Fast, honest, and the price matched the written estimate exactly. Would call GXG again for our next project."
"Professional from the first call to the final walkthrough. Our home looks brand new."
"Great communication throughout the whole project and the crew cleaned up every day before leaving."
"Would recommend GXG to anyone in Homestead looking for quality work at a fair price."